Revision 15-4; Effective October 1, 2015
All Programs
The due date and final due date entries are shown in the following table. Note: If the 10th or 30th day falls on a non-workday, the due date is the next workday. If the due date is not an HHSC workday (on a weekend or a holiday), the due date advances to the next HHSC workday.
TANF
EDG Action |
Due Date |
Final Due Date |
Application |
10 days |
- 30 days, or
- 10th day if 10 days end after 30th day
|
Complete redetermination |
10 days |
10 days |
Incomplete redetermination (including the addition of a household member) |
10 days |
10 days |
SNAP
EDG Action |
Due Date |
Final Due Date |
Application |
10 days* |
- 30 days, or
- 10th day if 10 days end after 30th day
|
Untimely redetermination (including adding a person at untimely redetermination) |
10 days* |
- 30 days, or
- 10th day if 10 days end after 30th day
|
Timely redetermination (including adding a person at timely redetermination) |
10 days* |
- last workday of last benefit month, or
- 10th day if 10 days end after last benefit month
|
Incomplete redetermination (including adding a person at incomplete redetermination) |
10 days |
10 days |
* For SNAP EDGs pended for a missed appointment, the 10-day due date is calculated from the date the form is mailed, usually two days after the H1020-MA is triggered by TIERS or TLM entries. The two additional days for mail time when sending a Form H1020-MA in TIERS is only applicable to SNAP EDGs pended for a missed appointment.
TP 08, TP 43, TP 44 and TP 48
EDG Action |
Due Date |
Final Due Date |
Application |
10 days |
- 30 days, or
- 10th day if 10 days end after 30th day
|
Complete redetermination |
10 days |
- 30 days or by cutoff in the last benefit month of certification, whichever is later; or
- 10th day if 10 days end after 30th day
|
Incomplete redetermination (including the addition of a household member) |
10 days |
10 days |
TP 40
EDG Action |
Due Date |
Final Due Date |
Application |
10 days |
- 15 work days, or
- 10th day if 10 days end after 15th work day
|
TA 31, TP 34, TP 35, TP 36, TP 56 and TP 32
EDG Action |
Due Date |
Final Due Date |
Application |
10 days |
- 30 days, or
- 10th day if 10 days end after 30th day
|